E-Newsletter
Subscribe Now
  ABOUT US   |   CONTACT US   |   SUBSCRIPTION CENTRE   |   ADVERTISE   |   SITEMAP
MAGAZINE
Current Issue
Past Issues
News Archives
Web Exclusives
 
MARKETPLACE
Job Board
Classifieds
Product News
COMMUNITY
Blog
Events
 
RESOURCES
E-Newsletter
Links
Sitemap
 
A solution for biomass abrasion

Biomass fuels have distinct properties that require innovative handling solutions.

Written by Abresist Corporation   
Sept. 2, 2011, Quebec City – Over the past 10 years, the landscape of the North American pulp and paper industry has seen a dramatic change. The addition of biomass boilers has been a popular choice for energy cost reduction. The forest industry now meets more than half its energy needs with self-generated biomass wastes. Although typically defined as wood residues such as bark or hog fuel, biomass also includes the plant effluent, de-inked mud, and other residues.

White Birch Papers
 
The White Birch Paper plant in Quebec City is not unlike many other newspaper paper mills in North America. To survive, it took the necessary steps of modernizing the plant. With the same energy concerns, it installed a high-efficiency biomass boiler in 2006 to decrease energy costs. One of the keys to high-efficiency boilers is to pre-dry the biomass before feeding into the boiler. This is accomplished at White Birch Paper using a rotary dryer followed by ducting up to two 50 foot tall (15 m) cyclones that sit 130 feet (40 m) off the ground. The larger particles fall out of the rotary dryer onto a conveyor, which then feeds into the boiler. The hot air and fines from the outlet are sucked up into the cyclones where the fines are separated and sent to the boiler while the hot air is sent back to the feed end of the rotary dryer to pre-dry the biomass.

The biomass comprises 40% plant effluent and 50% de-inked mud. The two cyclones are made of 3/16 inch thick SS304 to deal with the slightly corrosive (SO2) plant effluent. The cyclones operate under negative pressure (air pulled through and not pushed) because of the high flammability of the dried effluent and are equipped with an extinguishing system of water nozzles. Only one fire has occurred since commissioning, and this was due to leaky seals on the rotary valves and flange connections. Normal operating temperature at the top of the inlet is 95°C and 65°C at the cone outlets.

 cyclone  
Signs of wear
After 18 months of operation, the cyclones started showing signs of wear, requiring the replacement of several sections. Replaceable liners made of AR400 steel plates were installed for the inlet and upper barrel section. The lower 10 foot diameter (3 m) cone was also replaced and fabricated using AR400 plate.

Over the following year, wear continued to occur in both cyclones, requiring several maintenance interventions. Due to all the patching and uneven surfaces, the wear rate continued to increase, becoming a cause for concern.

The steam plant maintenance superintendent at the time had heard about a cyclone-lining project completed a year earlier at a nearby cement plant using Kalcret, a cement bonded wear compound. He inquired about the possibility of doing the same with White Birch Paper’s cyclones. Initial discussions about lining the inside of the cyclones with Kalcret were held in June of 2009, but due to short outage periods, the decision was taken to install AR liners during the September outage.

An inspection in January 2010 showed severe wear on all the AR liners, and the concern was that the original steel would be too thin to receive any more liners.

A solution
After several more discussions and meetings, it was concluded that lining the cyclones with Kalcret offered two major advantages: the cyclones would not need replacing, representing a significant cost savings, and the logistics were simpler.

The contract was awarded to Abresist Kalenborn Inc. of Pointe-Claire, Quebec, to line the bifurcated inlet section and both cyclones, an area totaling approximately 3,000 square-feet. The turnkey project was handled entirely by the Canada Kalprotect installation team, including the mobilization of cranes, scaffolding, and installation of all materials.

It was determined that Kalcret-BTS sprayable material would be used for each entire cyclone, with the exception of the bifurcated inlet area and lower cones. For safe and proper installation of the scaffolding, the first three sections of cones were removed and lowered to ground level. These lower cones would be completely replaced with new steel lined with Kalcret-BTX trowellable compound.

A wire mesh anchoring system was installed on all surfaces receiving the Kalcret wear compound. The inlet area and cyclone roofs were lined with the BTX trowellable Kalcret, and the bull nose was protected using an engineered Kalocer ceramic tile.

coating
 
Using the spraying equipment, quick work was made of the remaining 2000 square-feet, where Kalcret-BTS was applied. The new lower cones, now lined with Kalcret-BTX, were then positioned back into place and reassembled. Final touch-ups and one final site cleanup were followed by demobilization on schedule.

According to Louis Senechal, project manager, “The benefits of the Kalcret lining were noticed immediately after startup, as the operators were able to control the temperature and airflow much more effectively, which will allow for a more precise and efficient operation of the boiler.”

Increases in equipment wear life, as well as an improved operating efficiency, were just two of the benefits of the Kalcret abrasion resistant wear compound.

Lining the remaining 1000 square-feet of duct leading into the cyclones is already being discussed for the next outage.