July 30, 2018 - OPG and the Independent Electricity System Operator (IESO) are taking action to help reduce all Ontarian’s electricity bills by reviewing operations to keep costs low for customers. 

 

In late May 2018, significant corrosion damage was found to the boiler at Thunder Bay Generating Station, making the plant non-operational. Because of the high capital repair costs, high operational costs and limited time remaining on the IESO contract for Thunder Bay Generating Station, OPG and IESO determined that shutting down the station now is in the best interests of electricity customers.  


Repairs to the Thunder Bay Generating Station would take approximately six months, leaving only one year remaining for the IESO contract. Because of a lack of demand, Thunder Bay Generating Station is rarely used for electricity generation. Based on historical annual average operational days, it is expected that the repaired boiler would only be used for 2.5 days.   

This decision will save Ontario electricity customers $40 million and avoid $5 million in costs to OPG.  

No OPG employee will lose their job by closing Thunder Bay Generating Station. OPG is in discussions with employee unions on redeployment opportunities for affected staff and work reassignments.

Add comment


Security code
Refresh

Subscription Centre

 
New Subscription
 
Already a Subscriber
 
Customer Service
 
View Digital Magazine Renew

Most Popular

We are using cookies to give you the best experience on our website. By continuing to use the site, you agree to the use of cookies. To find out more, read our Privacy Policy.