UK biomass use continued to increase in 2010

July 14, 2011
By Argus Media

July 14, 2011, London, UK – The proportion of the UK's electricity generated from biomass in co-firing power plants rose by 39% to 2.5 TWh in 2010, compared with 1.8 TWh one year earlier.

July 14, 2011, London, UK – The proportion
of the UK's electricity generated from biomass in co-firing power plants rose
by 39% to 2.5 TWh in 2010, compared with 1.8 TWh one year earlier. Biomass
installed capacity totalled 2.1 GW in 2010, rising from 1.9 GW in 2009,
according to UK Department of Energy and Climate Change (DECC) figures. Generators
in the UK could add an additional 4 GW of capacity to the grid before 2014 if all
planned projects go ahead.

Several UK biomass projects are awaiting
the outcome of DECC's renewable obligation certificates (ROCs) banding review,
which is expected to be announced on July 19, before committing to
construction. Many projects say that if the ROCs awarded to dedicated biomass
plants are not increased to 1.75/MWh from 1.5/MWh, the projects may have to be
abandoned because they will not be financially feasible.

Please visit ArgusMedia.com for more information.

Copyright © 2012 Argus Media Ltd. All rights reserved. By reading
this article, you agree that you will not copy or reproduce any part of
its contents (including, but not limited to single prices or any other
individual items of data) in any form or for any purpose whatsoever
without prior consent of the publisher.

Advertisement

Print this page

Advertisement

Stories continue below


Related