Canadian Biomass Magazine

Waterloo, Ont., CHP facilities behind Canadian consulting engineering award

December 16, 2022
By Canadian Consulting Engineer

Photo: Jacobs

A consulting engineering firm behind the Regional Municipality of Waterloo’s project to install cogeneration facilities at three of its wastewater treatment plants in Ontario has won a national award.

Canadian Consulting Engineer and the Association of Consulting Engineering Companies – Canada (ACEC-Canada) handed out the 54th annual Canadian Consulting Engineering Awards at a celebration in Ottawa on Thursday, Nov 3.

Jacobs received an Award of Excellence in the Natural Resources, Mining, Industry and Energy category for the cogeneration project.

The regional municipality operates several conventional wastewater treatment plants (WWTPs) that produce digester gas as waste byproduct. Jacobs, along with teammates CIMA+ and Eramosa Engineering, led design and services during construction for the installation of cogeneration facilities at the region’s three largest WWTPs in Waterloo, Kitchener and Galt, Ont.

Advertisement

These facilities combust the digester gas to produce electricity and heat. The resulting energy is used on-site, thereby reducing carbon dioxide (CO2) emissions and the cost of externally provided electricity and natural gas.

Jacobs completed the following scope of work for all three sites:

  • Conceptual and preliminary design of cogeneration facilities.
  • Obtaining regulatory approvals and permits.
  • Co-ordination with utilities and provincial agencies to secure funding incentives.
  • Detailed design, with region reviews to facilitate input from operations staff.
  • Pre-selections for the cogeneration engine supply and the gas conditioning system supply.
  • Tender period assistance, project management, contract administration and site inspection services during the two-year construction period.
  • Participation in commissioning and training of operations staff for major systems.
  • Post-construction services, including record drawings, addressing deficiencies and transferring the operation to the region.

The engineers at Jacobs used innovative technologies to deliver an environmentally significant project that aligned with the region’s goals to become a sustainable community, as outlined in its greenhouse gas (GHG) inventory and action plan, which included a 10 per cent reduction of 2009 emission levels by the year 2019. (While this project was completed after 2019, it exemplifies continuing improvement by the region to optimize the use of renewable energy resources.) The economic feasibility of this project depended on government and utility incentive programs.

The pre-purchasing process allowed the Jacobs team and the region to develop emission and efficiency goals for the cogeneration engines and put them out for tender. The successful bidder was GAL Power, a vendor that supplied the combined heat and power (CHP) units from Germany; biogas use is much more common in Europe than in North America.

Jacobs’ practical and innovative design offered both economic and environmental benefits to the region and its residents, including the offsetting of electricity costs for the sites and the reduction of GHG emissions. By way of example, if digester gas production at a site is low or unavailable, the cogeneration facilities have the capability to run on natural gas or a blend of natural gas and digester gas.

One size does not fit all

The Jacobs team worked with W.A. Stephenson Mechanical Contractors during construction to manage the schedule and budget. In-house project management tools were used to ensure all milestones were met.

The project had a high level of complexity, as the three sites entailed different existing conditions, which had to be evaluated in the approval and conceptual design phases, so the detailed design would provide a constructable and cost-effective solution for all of the sites. The structures involved had to be flood-proof, for example, due to their proximity to watercourses; and the gas quality and quantity varied, which needed to be considered from a process perspective to size the generator engines appropriately and obtain Technical Standards and Safety Authority (TSSA) digester gas installation approvals.

Concrete work

The firm worked closely with the contractor to ensure construction proceeded on schedule, so the project would meet its funding deadlines. Photo courtesy Jacobs.

Construction management was also complicated due to the different parties involved. Each of the three sites had its own operational staff and operated under a different natural gas authorities and electrical local distribution company (LDC). Hurdles were overcome through diligent and frequent communications within the team and with various project stakeholders.

Another challenge was delivering the project in time, to meet deadlines set by the provincial and federal governments for the region to secure project funding. Due to the global pandemic, equipment and material deliveries were delayed. This challenge was overcome through proactive actions taken by the project team – including the region, Jacobs, the contractor and suppliers – to identify and secure critical path items.

Enhancing efficiency

The Galt and Waterloo WWTPs’ cogeneration facilities each generate 600 kilowatt-electric (kWe) capacity, which delivers more than 33 per cent of their respective electrical loads, while the Kitchener facility generates 800 kWe, more than 70 per cent of its load.

The generated heat is transferred to the plants’ hot water systems. It is then used to heat the buildings and digester sludge, reducing the natural gas load to the boilers.

Before the installation of the cogeneration facilities, digester gas was inefficiently used in boilers, with excess sent to flare. The complete combustion of digester gas releases CO2 into the atmosphere, but incomplete combustion results in the emission of methane, a GHG with 25 times greater global warming potential (GWP).

When the cogeneration facilities are running 100 per cent on biogas, the reduction of GHG emissions compared to pre-construction levels is equivalent to 934 tonnes of CO2 for Waterloo, 425 tonnes for Kitchener and 554 tonnes for Galt, annually.

Additionally, the cogeneration facilities include gas conditioning upstream of the engine generators and exhaust treatment equipment downstream. Before the blend of digester gas and natural gas is combusted in the engine generator, it is dried, filtered and cooled by the gas conditioning system to remove constituents that may hinder the efficiency or reliability of the combustion process. Similarly, exhaust from the generator engine is treated with urea to lower the concentration of harmful constituents emitted to the atmosphere.

Typical energy recovery of the cogeneration facilities is 70 per cent of digester gas energy value, with 35 per cent as electricity and 35 per cent as heat.


This article was originally published by Canadian Consulting Engineer here. Republished with permission.


Print this page

Advertisement

Stories continue below